Gold Coast City Council has a new procedure for building near stormwater (BOSW) applications, which requires the lodgement of
» the engineer’s foundation design;
» CCTV survey video; and
» written report at pre & post construction stages.
A bond of $5000 minimum is also required, refundable on satisfactory completion of works.
Council is not charging a fee for BOSW applications at this stage.
NCC 2022, effective from May 2023, revised shower floor grading to be minimum 1:80 to maximum 1:50. This applies to all States and is irrespective…
Brisbane City Council has now published further information about changes to siting variations which can be found at: https://www.brisbane.qld.gov.au/planning-and-building/do-i-need-approval/types-of-approval/building-near-the-boundary
From 1 July 2022, the Council fee for a siting relaxation will increase from $610 to $640. The current $610 fee applies irrespective of the…